Town of Arcadia Awards Construction Contract to Kordich Construction Inc (March 2023)
Town of ArcadiaCity · LA- Disclosed value
- $570,650, plus a 10% construction contingency (total up to $627,715)
- From agenda
- Approved
- Mar 7, 2023
The 30-second brief
The Arcadia City Council approved a construction contract with Kordich Construction, Inc. for $570,650 plus a 10% contingency, to replace a section of sewer main on Santa Anita Avenue. The project will upgrade existing infrastructure from 8-inch to 10-inch pipe to accommodate future demands.
Kordich Construction Inc holds this construction contract with Town of Arcadia. Its other public contracts on record include work for City of La Habra and City of Los Angeles - LA Sanitation and Environment.
Term as filed: Approximately May 2023 through July 2023 (60 calendar days from notice to proceed).
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $570,650, plus a 10% construction contingency (total up to $627,715)
- Document date
- March 7, 2023
- Term
- Approximately May 2023 through July 2023 (60 calendar days from notice to proceed)
- Vendor
- Kordich Construction Inc
- Agency
- Town of Arcadia
- Source document
- town-of-arcadia-agenda-2023-03-07_147.pdf (Agenda)
Kordich Construction Inc's other public contracts
More Town of Arcadia contracts
Questions about this contract
Who was awarded the construction contract by Town of Arcadia?
Kordich Construction Inc was awarded this construction contract by Town of Arcadia, as recorded on March 7, 2023. The contract value is $570,650, plus a 10% construction contingency (total up to $627,715).
How much is the Kordich Construction Inc contract with Town of Arcadia worth?
The Kordich Construction Inc contract with Town of Arcadia is valued at $570,650, plus a 10% construction contingency (total up to $627,715), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in town-of-arcadia-agenda-2023-03-07_147.pdf (Agenda), dated March 7, 2023 from Town of Arcadia. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Kordich Construction Inc hold?
Kordich Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Town of Arcadia currently buying?
Explore Town of Arcadia's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.