Spyglass Tank Slope Project Completed by Trinity Construction
Trusted by teams at
Description
The Spyglass Water Tank Site Slope Stabilization Project, performed by Trinity Construction, was accepted as complete after ten change orders, finalizing at $1,443,588.82.
Contract Details
Contract Amount
$1,443,588.82 (original $1,359,051.82 + $84,537 in 10 change orders)
Vendor
TRINITY CONSTRUCTION
Agency
Lake Arrowhead Community Services District, CA
Contract Type
CONSTRUCTION
Document Date
February 24, 2026
Contract Term
Project duration: Awarded July 22, 2025; accepted complete February 24, 2026
Renewal Date
2026-02-24
Renewal Info
Ten change orders, including line item reconciliation and scope adjustments; contract finalized and closed.
More from TRINITY CONSTRUCTION
Issuing Agency
Special District
Lake Arrowhead, CA
More from Lake Arrowhead Community Services District
Lake Arrowhead Community Services District AgendaPacket Board of Directors Meeting 2026-05-26
Lake Arrowhead Community Services District AgendaPacket Board of Directors Meeting 2026-05-26
Lake Arrowhead Community Services District AgendaPacket Board of Directors Meeting 2026-05-26
Lake Arrowhead Community Services District AgendaPacket Board of Directors Meeting 2026-05-26
Lake Arrowhead Community Services District Meeting Agenda April 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.