Clyde amends Hyatt Pipeline water main contract
- Disclosed value
- Net decrease of $44.40 (new total Contract Price $1,006,769.20)
- From minutes
- Document date
- Nov 18, 2024
The 30-second brief
The Town of Clyde approved Change Order No. 2 – Final with Hyatt Pipeline, LLC for the Charles Street Water Main Extension project, resulting in a net contract price decrease of $44.40 and a revised total of $1,006,769.20. The amendment covers additional paving and overlay and adjustments for unused quantities with no change to project completion dates.
Hyatt Pipeline LLC holds this construction contract with Town of Clyde. Its other public contracts on record include work for Town of Canton and City of Brevard.
Term as filed: Original: 150 days substantial completion / 180 days final payment; with all change orders: 300 days (Substantial completion by August 21, 2024) / 330 days (Ready for final payment by September 20, 2024).
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Net decrease of $44.40 (new total Contract Price $1,006,769.20)
- Document date
- November 18, 2024
- Term
- Original: 150 days substantial completion / 180 days final payment; with all change orders: 300 days (Substantial completion by August 21, 2024) / 330 days (Ready for final payment by September 20, 2024)
- Vendor
- Hyatt Pipeline LLC
- Agency
- Town of Clyde
- Source document
- Town of Clyde Mayor and Board of Aldermen Meeting Minutes November 18 2024 (Minutes)
Hyatt Pipeline LLC's other public contracts
More Town of Clyde contracts
Questions about this contract
Who was awarded the construction contract by Town of Clyde?
Hyatt Pipeline LLC was awarded this construction contract by Town of Clyde, as recorded on November 18, 2024. The contract value is Net decrease of $44.40 (new total Contract Price $1,006,769.20).
How much is the Hyatt Pipeline LLC contract with Town of Clyde worth?
The Hyatt Pipeline LLC contract with Town of Clyde is valued at Net decrease of $44.40 (new total Contract Price $1,006,769.20), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Town of Clyde Mayor and Board of Aldermen Meeting Minutes November 18 2024 (Minutes), dated November 18, 2024 from Town of Clyde. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Hyatt Pipeline LLC hold?
Hyatt Pipeline LLC may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Town of Clyde currently buying?
Explore Town of Clyde's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.