South Granville Water And Sewer Authority Executive Director Monthly Project Update Report May 2026

Park Construction advancing I-85 sewer CP#2

Not to exceed $30.24M (USDA-supported) for CP#2 overallSouth Granville Water And Sewer AuthorityPARK CONSTRUCTION NC INCMay 5, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Park Construction, NC, Inc. is constructing CP#2 of SGWASA’s I‑85 sewer improvements under a not‑to‑exceed $30.24 million USDA-supported budget. Work on the Southern Interceptor began November 1, 2025 and is currently on schedule and within budget.

Contract Details

Contract Amount

Not to exceed $30.24M (USDA-supported) for CP#2 overall

Vendor

PARK CONSTRUCTION NC INC

Agency

South Granville Water And Sewer Authority, NC

Contract Type

CONSTRUCTION

Document Date

May 5, 2026

Contract Term

Construction started 11/1/25; project timeline 2025–2028

Renewal Date

2028-12-31

Renewal Info

Northern Interceptor portion (~$8M) deferred; future Board decision may authorize additional work or amendments.