Union Sanitary District Awards $21,135,320 Construction Contract to Clark Construction Group – California LP (May 2026)
- Disclosed value
- $21,135,320
- From agendapacket
- Approved
- May 26, 2026
The 30-second brief
Union Sanitary District formally accepted the completed Standby Power Generation System Upgrade Project constructed by Clark Construction Group – California, LP under a $21,135,320 contract. The 760‑day project began in March 2022 and reached substantial completion in April 2025.
Clark Construction Group – California LP holds this construction contract with Union Sanitary District. Its other public contracts on record include work for City of Burbank and Ontario International Airport Authority.
Term as filed: 760-day project; Notice to Proceed March 14, 2022; substantial completion April 29, 2025.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $21,135,320
- Document date
- May 26, 2026
- Term
- 760-day project; Notice to Proceed March 14, 2022; substantial completion April 29, 2025
- Agency
- Union Sanitary District
- Source document
- Union Sanitary District Agenda Packet 2026-05-26 (AgendaPacket)
Clark Construction Group – California LP's other public contracts
More Union Sanitary District contracts
Questions about this contract
Who was awarded the construction contract by Union Sanitary District?
Clark Construction Group – California LP was awarded this construction contract by Union Sanitary District, as recorded on May 26, 2026. The contract value is $21,135,320.
How much is the Clark Construction Group – California LP contract with Union Sanitary District worth?
The Clark Construction Group – California LP contract with Union Sanitary District is valued at $21,135,320, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in Union Sanitary District Agenda Packet 2026-05-26 (AgendaPacket), dated May 26, 2026 from Union Sanitary District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Clark Construction Group – California LP hold?
Clark Construction Group – California LP may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Union Sanitary District currently buying?
Explore Union Sanitary District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.