Village of Columbus Grove Council Meeting Minutes April 2026

Mainline water project progress with Miller contracting

Columbus Grove villageMILLER CONTRACTINGApril 13, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Village of Columbus Grove discussed ongoing work by Miller contracting on the mainline water project, noting that 75% of the pipe is installed but the contractor is behind schedule due to weather and unforeseen issues. All installed sections have passed pressure testing as the project continues toward completion.

Contract Details

Vendor

MILLER CONTRACTING

Agency

Columbus Grove village, OH

Contract Type

CONSTRUCTION

Document Date

April 13, 2026