Hay Creek Interceptor contract amended for trail work
- Disclosed value
- Increase of $153,220.49 (new total $7,584,390.79)
- From contract
- Document date
- Aug 11, 2025
The 30-second brief
The City of Bismarck issued Change Order No. 3 with S. J. Louis Construction, Inc. for the Hay Creek Interceptor project, increasing the contract by $153,220.49 for additional trail replacement work. The amendment extends the final completion date by 14 days to July 14, 2026 while keeping the substantial completion date unchanged.
S. J. Louis Construction Inc holds this construction contract with Bismarck-Mandan MPO. Its other public contracts on record include work for Central Oklahoma Transportation and Parking Authority and City of Oklahoma.
Term as filed: Final payment date extended from June 30, 2026 to July 14, 2026; Substantial Completion remains December 29, 2025.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Increase of $153,220.49 (new total $7,584,390.79)
- Document date
- August 11, 2025
- Term
- Final payment date extended from June 30, 2026 to July 14, 2026; Substantial Completion remains December 29, 2025
- Agency
- Bismarck-Mandan MPO
- Source document
- bismarck-mandan-mpo-change-order-3-hay-creek-interceptor_073.pdf (Contract)
S. J. Louis Construction Inc's other public contracts
More Bismarck-Mandan MPO contracts
Questions about this contract
Who was awarded the construction contract by Bismarck-Mandan MPO?
S. J. Louis Construction Inc was awarded this construction contract by Bismarck-Mandan MPO, as recorded on August 11, 2025. The contract value is Increase of $153,220.49 (new total $7,584,390.79).
How much is the S. J. Louis Construction Inc contract with Bismarck-Mandan MPO worth?
The S. J. Louis Construction Inc contract with Bismarck-Mandan MPO is valued at Increase of $153,220.49 (new total $7,584,390.79), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in bismarck-mandan-mpo-change-order-3-hay-creek-interceptor_073.pdf (Contract), dated August 11, 2025 from Bismarck-Mandan MPO. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does S. J. Louis Construction Inc hold?
S. J. Louis Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Bismarck-Mandan MPO currently buying?
Explore Bismarck-Mandan MPO's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.