CONTRACTAMENDED

Change order and final payment for sewer project

City of Clifton logoCity of Clifton
Disclosed value
$4,450.00 (change order); final adjusted contract sum $754,858.00; final payment due $63,068.16
From agenda
Document date
Apr 21, 2026

The 30-second brief

What it covers

The City of Clifton plans to approve Change Order No. 2 and final closeout for the Ravine Park Sanitary Sewer Improvements contract with John Garcia Construction, increasing the contract by $4,450.00 for unforeseen sewer cleaning and lining work and bringing the total to $754,858.00. The action also authorizes final payment of $63,068.16 after the contractor posted a two-year maintenance bond for 10% of the final contract amount.

Who holds it

John Garcia Construction holds this construction contract with City of Clifton. Its other public contracts on record include work for Morris County and Borough of Essex Fells.

What happens next

Term as filed: Two-year maintenance bond period posted by contractor.

See who signed off on this contract.

See who signed off

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$4,450.00 (change order); final adjusted contract sum $754,858.00; final payment due $63,068.16
Document date
April 21, 2026
Term
Two-year maintenance bond period posted by contractor
Source document
City of Clifton Council Meeting Agenda April 2026 (Agenda)

John Garcia Construction's other public contracts

More City of Clifton contracts

Questions about this contract

Who was awarded the construction contract by City of Clifton?

John Garcia Construction was awarded this construction contract by City of Clifton, as recorded on April 21, 2026. The contract value is $4,450.00 (change order); final adjusted contract sum $754,858.00; final payment due $63,068.16.

How much is the John Garcia Construction contract with City of Clifton worth?

The John Garcia Construction contract with City of Clifton is valued at $4,450.00 (change order); final adjusted contract sum $754,858.00; final payment due $63,068.16, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in City of Clifton Council Meeting Agenda April 2026 (Agenda), dated April 21, 2026 from City of Clifton. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does John Garcia Construction hold?

John Garcia Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is City of Clifton currently buying?

Explore City of Clifton's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →