GCWW water main project change order approved
- Disclosed value
- Change Order Amount: $161,980.00 (New Total Project Cost: $671,537.33; GCWW paying $400,704.67)
- From minutes
- Document date
- May 18, 2026
The 30-second brief
The Village Council approved Ordinance 6-2026, authorizing a $161,980.00 change order with Greater Cincinnati Water Works for additional curb and ADA ramp work on the Water Main Replacement Project, bringing the total project cost to $671,537.33. GCWW is contributing $400,704.67 toward the roadway, reducing the Village’s overall cost compared to initial estimates.
Greater Cincinnati Water Works holds this construction contract with Little Miami Joint Fire & Rescue District. Its other public contracts on record include work for Cincinnati Public Schools and Terrace Park village.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Change Order Amount: $161,980.00 (New Total Project Cost: $671,537.33; GCWW paying $400,704.67)
- Document date
- May 18, 2026
- Source document
- Village of Fairfax Council Meeting Minutes 2026-05-18 (Minutes)
Greater Cincinnati Water Works's other public contracts
More Little Miami Joint Fire & Rescue District contracts
Questions about this contract
Who was awarded the construction contract by Little Miami Joint Fire & Rescue District?
Greater Cincinnati Water Works was awarded this construction contract by Little Miami Joint Fire & Rescue District, as recorded on May 18, 2026. The contract value is Change Order Amount: $161,980.00 (New Total Project Cost: $671,537.33; GCWW paying $400,704.67).
How much is the Greater Cincinnati Water Works contract with Little Miami Joint Fire & Rescue District worth?
The Greater Cincinnati Water Works contract with Little Miami Joint Fire & Rescue District is valued at Change Order Amount: $161,980.00 (New Total Project Cost: $671,537.33; GCWW paying $400,704.67), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Village of Fairfax Council Meeting Minutes 2026-05-18 (Minutes), dated May 18, 2026 from Little Miami Joint Fire & Rescue District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Greater Cincinnati Water Works hold?
Greater Cincinnati Water Works may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Little Miami Joint Fire & Rescue District currently buying?
Explore Little Miami Joint Fire & Rescue District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.