Kiewit Continues Construction Role on Project Health
- Disclosed value
- Total Project Cost of $2.748 billion
- From agendapacket
- Document date
- Nov 20, 2026
The 30-second brief
The University of Nebraska continues its Integrated Project Delivery Agreement with Kiewit Building Group, Inc. for Project Health, a planned academic medical center and parking garage. The project has a stated total project cost of $2.748 billion and is currently estimated to conclude in 2032.
Kiewit Building Group Inc holds this construction contract with University of Nebraska | State of Nebraska. Its other public contracts on record include work for Tacoma Public Schools.
Term as filed: Ongoing; Project Health is currently estimated to conclude in 2032.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Total Project Cost of $2.748 billion
- Document date
- November 20, 2026
- Term
- Ongoing; Project Health is currently estimated to conclude in 2032
- Source document
- University of Nebraska AgendaPacket Emergency Board Meeting 2026-11-20 (AgendaPacket)
Kiewit Building Group Inc's other public contracts
More University of Nebraska | State of Nebraska contracts
Questions about this contract
Who was awarded the construction contract by University of Nebraska | State of Nebraska?
Kiewit Building Group Inc was awarded this construction contract by University of Nebraska | State of Nebraska, as recorded on November 20, 2026. The contract value is Total Project Cost of $2.748 billion.
How much is the Kiewit Building Group Inc contract with University of Nebraska | State of Nebraska worth?
The Kiewit Building Group Inc contract with University of Nebraska | State of Nebraska is valued at Total Project Cost of $2.748 billion, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in University of Nebraska AgendaPacket Emergency Board Meeting 2026-11-20 (AgendaPacket), dated November 20, 2026 from University of Nebraska | State of Nebraska. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Kiewit Building Group Inc hold?
Kiewit Building Group Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is University of Nebraska | State of Nebraska currently buying?
Explore University of Nebraska | State of Nebraska's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.