- $33,352,190.00 (Original GMP); Adjusted Contract Amount $33,414,983.00
- From report
- Document date
- May 1, 2026
The 30-second brief
Greater Clark County Schools continues its GMP construction contract with DS for the Jeffersonville High School Natatorium, with an adjusted value of $33.41 million and 64% completion as of March 31, 2026. The 29‑month project has 7 months remaining, supported by an active construction manager contingency for ongoing change orders and scope adjustments.
DS holds this construction contract with Greater Clark County Schools. Its other public contracts on record include work for Bratenahl village and City of Mayfield.
Term as filed: Total construction schedule 29 months; 22 months completed, 7 months remaining as of 3/31/2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $33,352,190.00 (Original GMP); Adjusted Contract Amount $33,414,983.00
- Document date
- May 1, 2026
- Term
- Total construction schedule 29 months; 22 months completed, 7 months remaining as of 3/31/2026
- Vendor
- DS
- Source document
- Greater Clark County Schools Report Jeffersonville High School Natatorium Board Update 2026-05-01 (Report)
DS's other public contracts
More Greater Clark County Schools contracts
Questions about this contract
Who was awarded the construction contract by Greater Clark County Schools?
DS was awarded this construction contract by Greater Clark County Schools, as recorded on May 1, 2026. The contract value is $33,352,190.00 (Original GMP); Adjusted Contract Amount $33,414,983.00.
How much is the DS contract with Greater Clark County Schools worth?
The DS contract with Greater Clark County Schools is valued at $33,352,190.00 (Original GMP); Adjusted Contract Amount $33,414,983.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Greater Clark County Schools Report Jeffersonville High School Natatorium Board Update 2026-05-01 (Report), dated May 1, 2026 from Greater Clark County Schools. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does DS hold?
DS may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Greater Clark County Schools currently buying?
Explore Greater Clark County Schools's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.