ERC proposes church remediation and demolition for GCCISD
- Disclosed value
- $391,157.32 (Remediation $148,584.32; Demolition $229,809.00; Hydro-Seeding $6,000.00; P & P Bond $6,764.00)
- From proposal
- Document date
- Jul 1, 2026
The 30-second brief
ERC submitted a $391,157.32 proposal to Goose Creek CISD to remediate asbestos-containing materials, demolish the former Harvest Time Church at 1715 Market in Baytown, and hydro-seed the site, with work anticipated to take roughly 15 business days for remediation. The offer, made under Cooperative Choice Partners contract 23/016MR-14, is valid for 60 days and includes full project supervision and bond coverage.
ERC holds this construction contract with Goose Creek Consolidated Independent School District. Its other public contracts on record include work for Golden Charter Academy and Atwater Elementary.
Term as filed: Approximately 15 business days for remediation; overall term not specified.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $391,157.32 (Remediation $148,584.32; Demolition $229,809.00; Hydro-Seeding $6,000.00; P & P Bond $6,764.00)
- Document date
- July 1, 2026
- Term
- Approximately 15 business days for remediation; overall term not specified
- Vendor
- ERC
- Source document
- Goose Creek CISD Proposal Remediation and Demolition of Harvest Time Church 2026-07-01 (Proposal)
ERC's other public contracts
More Goose Creek Consolidated Independent School District contracts
Questions about this contract
Who was awarded the construction contract by Goose Creek Consolidated Independent School District?
ERC was awarded this construction contract by Goose Creek Consolidated Independent School District, as recorded on July 1, 2026. The contract value is $391,157.32 (Remediation $148,584.32; Demolition $229,809.00; Hydro-Seeding $6,000.00; P & P Bond $6,764.00).
How much is the ERC contract with Goose Creek Consolidated Independent School District worth?
The ERC contract with Goose Creek Consolidated Independent School District is valued at $391,157.32 (Remediation $148,584.32; Demolition $229,809.00; Hydro-Seeding $6,000.00; P & P Bond $6,764.00), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a proposal record.
Where was this contract approved?
This contract appears in Goose Creek CISD Proposal Remediation and Demolition of Harvest Time Church 2026-07-01 (Proposal), dated July 1, 2026 from Goose Creek Consolidated Independent School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does ERC hold?
ERC may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Goose Creek Consolidated Independent School District currently buying?
Explore Goose Creek Consolidated Independent School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.