Collegedale Establishes Infrastructure District for EA Homes
- Disclosed value
- Estimated infrastructure cost of approximately $23 million; first-phase infrastructure estimated at approximately $9 million; total development estimated at approximately $100 million
- From agendapacket
- Document date
- Nov 10, 2026
The 30-second brief
The City of Collegedale approved Resolution #591 establishing the Chastain Commons Infrastructure Development District for EA Homes, LP. Future development agreements are planned to govern infrastructure construction and phased residential development, supported by special assessments of up to $1,800 per parcel annually for no more than 30 years.
Ea Homes LP holds this construction contract with City of Collegedale. Its other public contracts on record include work for City of Alpharetta and Fulton County.
Term as filed: Assessment-backed development period of not more than 30 years; development agreements to be entered into for the district or applicable phases.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Estimated infrastructure cost of approximately $23 million; first-phase infrastructure estimated at approximately $9 million; total development estimated at approximately $100 million
- Document date
- November 10, 2026
- Term
- Assessment-backed development period of not more than 30 years; development agreements to be entered into for the district or applicable phases
- Vendor
- Ea Homes LP
- Agency
- City of Collegedale
- Source document
- City of Collegedale AgendaPacket Special Called Meeting Packet November 10, 2026 (AgendaPacket)
More City of Collegedale contracts
Questions about this contract
Who was awarded the construction contract by City of Collegedale?
Ea Homes LP was awarded this construction contract by City of Collegedale, as recorded on November 10, 2026. The contract value is Estimated infrastructure cost of approximately $23 million; first-phase infrastructure estimated at approximately $9 million; total development estimated at approximately $100 million.
How much is the Ea Homes LP contract with City of Collegedale worth?
The Ea Homes LP contract with City of Collegedale is valued at Estimated infrastructure cost of approximately $23 million; first-phase infrastructure estimated at approximately $9 million; total development estimated at approximately $100 million, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agendapacket record.
Where was this contract approved?
This contract appears in City of Collegedale AgendaPacket Special Called Meeting Packet November 10, 2026 (AgendaPacket), dated November 10, 2026 from City of Collegedale. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Ea Homes LP hold?
Ea Homes LP may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Collegedale currently buying?
Explore City of Collegedale's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.