Skanska terminal expansion GMP amended for added scope
City of Redmond Airport DepartmentAirport Authority · OR- Disclosed value
- $143.7 million current approved construction costs; Bid Package #4 roughly $900,000 higher than original estimate; includes $1.7 million for furniture and $1.3 million for HVAC upgrade
- From agenda
- Document date
- Dec 18, 2025
The 30-second brief
Redmond Municipal Airport reported that general contractor Skanska USA’s fourth and final GMP package for the terminal expansion added $1.7 million in furniture and a $1.3 million HVAC upgrade, bringing approved construction costs to about $143.7 million. Despite the added scope, overall project costs remain below the original $150 million estimate due to favorable bid results.
Skanska USA holds this construction contract with City of Redmond Airport Department. Its other public contracts on record include work for Nashoba School District.
Hear about the next contract at City of Redmond Airport Department early.
Get pre-RFP alerts freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $143.7 million current approved construction costs; Bid Package #4 roughly $900,000 higher than original estimate; includes $1.7 million for furniture and $1.3 million for HVAC upgrade
- Document date
- December 18, 2025
- Vendor
- Skanska USA
- Source document
- Redmond Municipal Airport Committee Meeting Agenda December 2025 (Agenda)
Skanska USA's other public contracts
More City of Redmond Airport Department contracts
Questions about this contract
Who was awarded the construction contract by City of Redmond Airport Department?
Skanska USA was awarded this construction contract by City of Redmond Airport Department, as recorded on December 18, 2025. The contract value is $143.7 million current approved construction costs; Bid Package #4 roughly $900,000 higher than original estimate; includes $1.7 million for furniture and $1.3 million for HVAC upgrade.
How much is the Skanska USA contract with City of Redmond Airport Department worth?
The Skanska USA contract with City of Redmond Airport Department is valued at $143.7 million current approved construction costs; Bid Package #4 roughly $900,000 higher than original estimate; includes $1.7 million for furniture and $1.3 million for HVAC upgrade, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in Redmond Municipal Airport Committee Meeting Agenda December 2025 (Agenda), dated December 18, 2025 from City of Redmond Airport Department. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Skanska USA hold?
Skanska USA may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Redmond Airport Department currently buying?
Explore City of Redmond Airport Department's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.