MSA Approves Route 11 Waterline Change Order
- Disclosed value
- $114,377.78 change order; contract total increased from $2,466,020.54 to $2,580,398.32
- From minutes
- Document date
- Aug 25, 2026
- Renews
- Free account
The 30-second brief
Maury Service Authority approved a $114,377.78 change order with Randy Hostetter Excavating for electrical controls and backboards at the Houston Street Tank and vault. The amendment raises the Route 11 Waterline Improvements contract to $2.58 million and extends completion to October 27, 2026.
Randy Hostetter Excavating holds this construction contract with Maury Service Authority. Its other public contracts on record include work for City of Lexington.
The renewal date is on record. Get free alerts for pre-RFPs like this one, matched to what you sell.
Get pre-RFPs for work like this before the bid is out.
Get pre-RFP alerts freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $114,377.78 change order; contract total increased from $2,466,020.54 to $2,580,398.32
- Document date
- August 25, 2026
- Term
- 60-day extension; substantial completion moved to October 27, 2026 and final payment to November 26, 2026
- Renews
- On record
- Agency
- Maury Service Authority
- Source document
- Maury Service Authority Minutes Regular Board Meeting August 25, 2026 (Minutes)
Randy Hostetter Excavating's other public contracts
More Maury Service Authority contracts
Questions about this contract
Who was awarded the construction contract by Maury Service Authority?
Randy Hostetter Excavating was awarded this construction contract by Maury Service Authority, as recorded on August 25, 2026. The contract value is $114,377.78 change order; contract total increased from $2,466,020.54 to $2,580,398.32.
How much is the Randy Hostetter Excavating contract with Maury Service Authority worth?
The Randy Hostetter Excavating contract with Maury Service Authority is valued at $114,377.78 change order; contract total increased from $2,466,020.54 to $2,580,398.32, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Maury Service Authority Minutes Regular Board Meeting August 25, 2026 (Minutes), dated August 25, 2026 from Maury Service Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Randy Hostetter Excavating hold?
Randy Hostetter Excavating may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Maury Service Authority currently buying?
Explore Maury Service Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.