Ericstad Advances Firewall and Gym Wall Construction
- Document date
- Nov 13, 2026
- Term
- Ongoing as of November 13, 2026
The 30-second brief
Ericstad continued firewall, gym wall, and stairwell construction at Project Kyle Elementary. The work included the second-floor CMU firewall in Area A and the west gym area.
ERICSTAD holds this construction contract with Hays Consolidated Independent School District.
Term as filed: Ongoing as of November 13, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- November 13, 2026
- Term
- Ongoing as of November 13, 2026
- Vendor
- ERICSTAD
- Source document
- Hays CISD Report Construction Update - Weekly Progress Report 2026-11-13 (Report)
ERICSTAD's other public contracts
More Hays Consolidated Independent School District contracts
Questions about this contract
Who was awarded the construction contract by Hays Consolidated Independent School District?
ERICSTAD was awarded this construction contract by Hays Consolidated Independent School District, as recorded on November 13, 2026.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Hays CISD Report Construction Update - Weekly Progress Report 2026-11-13 (Report), dated November 13, 2026 from Hays Consolidated Independent School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does ERICSTAD hold?
ERICSTAD may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is Hays Consolidated Independent School District currently buying?
Explore Hays Consolidated Independent School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.