Clare awards Lake Shamrock Dam build to Fisher Contracting
Trusted by teams at
Description
The Clare City Commission approved Resolution 2026-043 awarding Fisher Contracting a construction contract for the Lake Shamrock Dam Project at $6,052,515 plus a 5% contingency. The project covers phased replacement of the dam and related water control infrastructure over an anticipated 6–7-month schedule.
Contract Details
Contract Amount
$6,052,515 plus 5% contingency of $302,626 (total construction $6,355,141)
Vendor
FISHER CONTRACTING
Agency
City of Claire, SD
Contract Type
CONSTRUCTION
Document Date
June 15, 2026
Contract Term
Approximately 6–7-month construction schedule, with potential winter shutdown and spring return for gate and pedestrian bridge installation
Renewal Info
Single-phase construction contract with a contingency; schedule anticipates a 6–7-month duration with possible winter shutdown and spring return for gate and pedestrian bridge installation. No formal renewal or extension options are stated.
More from FISHER CONTRACTING
More from City of Claire
City of Clare Agenda 2026-06-15
City of Clare StaffReport Waste Water Treatment Plant Gate Valve Replacement Bid 2026-06-15
City of Clare Agenda 2026-06-15
City of Clare Agenda 2026-06-15
City of Clare Agenda 2026-06-15
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.