City of Clare Staff Report Lake Shamrock Dam Project 2026-06-15

Clare awards Lake Shamrock Dam build to Fisher Contracting

$6,052,515 plus 5% contingency of $302,626 (total construction $6,355,141)City of ClaireFISHER CONTRACTINGJune 15, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Clare City Commission approved Resolution 2026-043 awarding Fisher Contracting a construction contract for the Lake Shamrock Dam Project at $6,052,515 plus a 5% contingency. The project covers phased replacement of the dam and related water control infrastructure over an anticipated 6–7-month schedule.

Contract Details

Contract Amount

$6,052,515 plus 5% contingency of $302,626 (total construction $6,355,141)

Vendor

FISHER CONTRACTING

Agency

City of Claire, SD

Contract Type

CONSTRUCTION

Document Date

June 15, 2026

Contract Term

Approximately 6–7-month construction schedule, with potential winter shutdown and spring return for gate and pedestrian bridge installation

Renewal Info

Single-phase construction contract with a contingency; schedule anticipates a 6–7-month duration with possible winter shutdown and spring return for gate and pedestrian bridge installation. No formal renewal or extension options are stated.