Boiler Replacement Change Order Recommended for Ryan Mechanical
- Disclosed value
- Net increase of $49,953.75; original contract $595,347.00; new contract amount $645,300.75
- From report
- Document date
- Nov 12, 2026
The 30-second brief
Clark County School District recommended a $49,953.75 change order for Ryan Mechanical, Inc.'s emergency boiler replacement project at Virgin Valley Elementary School. The change raises the contract from $595,347.00 to $645,300.75 to cover relocating the temporary boiler during construction.
Ryan Mechanical Inc holds this construction contract with Clark County School District. Its other public contracts on record include work for Shakopee Public School District and Las Vegas Convention And Visitors Authority.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Net increase of $49,953.75; original contract $595,347.00; new contract amount $645,300.75
- Document date
- November 12, 2026
- Vendor
- Ryan Mechanical Inc
- Source document
- Clark County School District Report Emergency Boiler Replacement Change Order 2026-11-12 (Report)
Ryan Mechanical Inc's other public contracts
More Clark County School District contracts
Questions about this contract
Who was awarded the construction contract by Clark County School District?
Ryan Mechanical Inc was awarded this construction contract by Clark County School District, as recorded on November 12, 2026. The contract value is Net increase of $49,953.75; original contract $595,347.00; new contract amount $645,300.75.
How much is the Ryan Mechanical Inc contract with Clark County School District worth?
The Ryan Mechanical Inc contract with Clark County School District is valued at Net increase of $49,953.75; original contract $595,347.00; new contract amount $645,300.75, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Clark County School District Report Emergency Boiler Replacement Change Order 2026-11-12 (Report), dated November 12, 2026 from Clark County School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Ryan Mechanical Inc hold?
Ryan Mechanical Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Clark County School District currently buying?
Explore Clark County School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.