CONTRACTONGOING

Archer Western Advances Wastewater Plant Expansion

City of Flowery Branch logoCity of Flowery Branch
Disclosed value
Approximately ninety percent of the project's value has been billed, with $330,000 remaining in the owner's contingency
From agendapacket
Document date
Aug 20, 2026

The 30-second brief

What it covers

Archer Western continues work on the City of Flowery Branch’s Wastewater Treatment Plant expansion, with substantial completion expected in September 2026 and final completion by November 11, 2026, and a deductive change order anticipated to return contingency funds to the city.

Who holds it

Archer Western holds this construction contract with City of Flowery Branch. Its other public contracts on record include work for City of Grapevine city and Timpanogos Special Service District.

What happens next

Term as filed: Substantial completion expected September 2026; final completion by November 11, 2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Approximately ninety percent of the project's value has been billed, with $330,000 remaining in the owner's contingency
Document date
August 20, 2026
Term
Substantial completion expected September 2026; final completion by November 11, 2026
Source document
City of Flowery Branch AgendaPacket City Council Meeting 2026-08-20 (AgendaPacket)

Archer Western's other public contracts

More City of Flowery Branch contracts

Questions about this contract

Who was awarded the construction contract by City of Flowery Branch?

Archer Western was awarded this construction contract by City of Flowery Branch, as recorded on August 20, 2026. The contract value is Approximately ninety percent of the project's value has been billed, with $330,000 remaining in the owner's contingency.

How much is the Archer Western contract with City of Flowery Branch worth?

The Archer Western contract with City of Flowery Branch is valued at Approximately ninety percent of the project's value has been billed, with $330,000 remaining in the owner's contingency, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in City of Flowery Branch AgendaPacket City Council Meeting 2026-08-20 (AgendaPacket), dated August 20, 2026 from City of Flowery Branch. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Archer Western hold?

Archer Western may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is City of Flowery Branch currently buying?

Explore City of Flowery Branch's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →

The coverage behind every signal

agencies covered
275,000+agencies covered
buying signals a week
400,000+buying signals a week
decision makers
2.6M+decision makers
in government spend tracked
$14T+in government spend tracked

Trusted by 200+ enterprise teams

Motive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logo