Metropolitan Nashville Airport Authority Operations Committee Agenda Packet May 2026

Major change order for employee and valet parking lot

$50,971,692 (including Change Order #3)Metropolitan Nashville Airport AuthorityJONES BROTHERSMay 13, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Operations Committee is asked to approve Change Order #3 with Jones Bros. for $10,036,192 on the Northeast Employee/Valet Storage Parking Lot, bringing the total contract to $50,971,692. The amendment covers unforeseen excavation and additional shot rock while replenishing the owner’s contingency.

Contract Details

Contract Amount

$50,971,692 (including Change Order #3)

Vendor

JONES BROTHERS

Agency

Metropolitan Nashville Airport Authority, TN

Contract Type

CONSTRUCTION

Document Date

May 13, 2026

Contract Term

December 18, 2025 – November 24, 2026 (342 calendar days)

Renewal Date

2026-11-24

Renewal Info

Change Order #3 increases the contract value by $10,036,192 and replenishes owner’s contingency to $4,000,000; prior Change Orders #1 and #2 did not change contract value.

More from JONES BROTHERS

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free