Change Order Increases Cost for Employee/Valet Lot

Original $40,935,500; Change Order #3 $10,036,192; Revised total $50,971,692Metropolitan Nashville Airport AuthorityJONES BROTHERSMay 19, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Staff requested approval of a $10,036,192 Change Order #3 with Jones Bros. for the Northeast Employee/Valet Storage Parking Lot to fund unforeseen excavation and rock import and restore contingency, raising the contract total to $50.97 million. The project remains scheduled for completion in November 2026.

Contract Details

Contract Amount

Original $40,935,500; Change Order #3 $10,036,192; Revised total $50,971,692

Vendor

JONES BROTHERS

Agency

Metropolitan Nashville Airport Authority, TN

Contract Type

CONSTRUCTION

Document Date

May 19, 2026

Contract Term

December 18, 2025 – November 24, 2026 (342 calendar days)

Renewal Date

2026-11-24

Renewal Info

Third change order increases contract value and replenishes contingency; contract completion date remains November 24, 2026.

More from JONES BROTHERS

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free