Main Street Reconstruction Contract Awarded to Coleman & Son
Trusted by teams at
Description
The Conway Selectboard awarded a $6,103,430.90 construction contract to Alvin J. Coleman & Son, Inc. for the NH Route 16/Main Street and NH Route 113 reconstruction project. Work will begin April 20, 2026, pause in winter, and is expected to be completed by October 2027 under the Federal Aid LPA Program.
Contract Details
Contract Amount
$6,103,430.90
Vendor
ALVIN J. COLEMAN & SON INC
Agency
Town of Conway, NH
Contract Type
CONSTRUCTION
Document Date
April 7, 2026
Contract Term
Construction start April 20, 2026, work through November 2026 and resume spring 2027 with anticipated end date of October 2027
Renewal Date
2027-10-31
Renewal Info
One-time construction contract for NHDOT Project CONWAY, X-A004(446), #40638, with anticipated completion by October 2027.
More from Town of Conway
Conway Board of Selectmen Meeting Minutes April 2026
Conway Board of Selectmen Meeting Minutes April 2026
Conway Board of Selectmen Meeting Minutes April 2026
Conway Board of Selectmen Meeting Minutes April 2026
Conway Board of Selectmen Meeting Minutes March 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.