CONTRACTAMENDED

Heller Spillway change order extends completion date

Williamsport Municipal Water Authority & Williamsport Sanitary Authority
Document date
Jan 28, 2026

The 30-second brief

What it covers

The Williamsport Municipal Water Authority approved Change Order #2 with Greenland Construction, Inc. for the Heller Spillway Project, adding a 145-day time extension with no additional cost. The substantial completion date shifts from December 27, 2025 to May 20, 2026 to accommodate a winter shutdown.

Who holds it

Greenland Construction Inc holds this construction contract with Williamsport Municipal Water Authority & Williamsport Sanitary Authority. Its other public contracts on record include work for Houtzdale Municipal (Water) Authority and Borough of Tyrone.

What happens next

Term as filed: Original term extended by 145 days; substantial completion moved from December 27, 2025 to May 20, 2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Document date
January 28, 2026
Term
Original term extended by 145 days; substantial completion moved from December 27, 2025 to May 20, 2026
Source document
Williamsport Municipal Water Authority Minutes of Regular Board Meeting 2026-01-28 (Minutes)

Greenland Construction Inc's other public contracts

More Williamsport Municipal Water Authority & Williamsport Sanitary Authority contracts

Questions about this contract

Who was awarded the construction contract by Williamsport Municipal Water Authority & Williamsport Sanitary Authority?

Greenland Construction Inc was awarded this construction contract by Williamsport Municipal Water Authority & Williamsport Sanitary Authority, as recorded on January 28, 2026.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Williamsport Municipal Water Authority Minutes of Regular Board Meeting 2026-01-28 (Minutes), dated January 28, 2026 from Williamsport Municipal Water Authority & Williamsport Sanitary Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Greenland Construction Inc hold?

Greenland Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

Show 1 more question

What is Williamsport Municipal Water Authority & Williamsport Sanitary Authority currently buying?

Explore Williamsport Municipal Water Authority & Williamsport Sanitary Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →

The coverage behind every signal

agencies covered
275,000+agencies covered
buying signals a week
400,000+buying signals a week
decision makers
2.6M+decision makers
in government spend tracked
$14T+in government spend tracked

Trusted by 200+ enterprise teams

Motive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logo