Clarifier Drive Equipment Proposal Submitted by ClearStream
Upper Montgomery Joint (Sewer) AuthoritySpecial District · Pennsburg, PA- Disclosed value
- $72,151
- From resolution
- Document date
- Nov 10, 2026
The 30-second brief
Upper Montgomery Joint Authority received a $72,151 proposal from ClearStream Environmental for a replacement primary clarifier drive. The proposal covers equipment, field measurement, checkout, and operating instruction for the wastewater treatment plant project.
Clearstream Environmental holds this equipment contract with Upper Montgomery Joint (Sewer) Authority. Its other public contracts on record include work for City of Independence and City of Dickinson.
Term as filed: Submittal drawings 4–6 weeks after receipt of purchase order; owner review 2 weeks; standard delivery 16–18 weeks after approved submittals; one-year equipment warranty.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Equipment
- Amount
- $72,151
- Document date
- November 10, 2026
- Term
- Submittal drawings 4–6 weeks after receipt of purchase order; owner review 2 weeks; standard delivery 16–18 weeks after approved submittals; one-year equipment warranty
- Source document
- Upper Montgomery Joint Authority Resolution 2026-10 WWTP Primary Clarifier Replacement Project 2026-11-10 (Resolution)
Clearstream Environmental's other public contracts
More Upper Montgomery Joint (Sewer) Authority contracts
Questions about this contract
Who was awarded the equipment contract by Upper Montgomery Joint (Sewer) Authority?
Clearstream Environmental was awarded this equipment contract by Upper Montgomery Joint (Sewer) Authority, as recorded on November 10, 2026. The contract value is $72,151.
How much is the Clearstream Environmental contract with Upper Montgomery Joint (Sewer) Authority worth?
The Clearstream Environmental contract with Upper Montgomery Joint (Sewer) Authority is valued at $72,151, covering equipment work.
What type of contract is this?
This is a Equipment contract, documented as a resolution record.
Where was this contract approved?
This contract appears in Upper Montgomery Joint Authority Resolution 2026-10 WWTP Primary Clarifier Replacement Project 2026-11-10 (Resolution), dated November 10, 2026 from Upper Montgomery Joint (Sewer) Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Clearstream Environmental hold?
Clearstream Environmental may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Upper Montgomery Joint (Sewer) Authority currently buying?
Explore Upper Montgomery Joint (Sewer) Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.