Mortenson Continues Permitting Work for Circuit Northwest
Port Of BremertonPublic Authority · Bremerton, WA- Document date
- Jul 14, 2026
The 30-second brief
Mortenson is continuing permitting work for the Port of Bremerton’s Circuit of the Northwest project. Final design is more than 90% complete, with construction mobilization targeted for the first quarter of 2027.
MORTENSON holds this construction contract with Port Of Bremerton. Its other public contracts on record include work for City of Surprise and City of Golden Valley.
Term as filed: Ongoing; construction mobilization targeted for Q1 2027.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- July 14, 2026
- Term
- Ongoing; construction mobilization targeted for Q1 2027
- Vendor
- MORTENSON
- Agency
- Port Of Bremerton
- Source document
- Port of Bremerton Minutes Regular Business Meeting July 14, 2026 (Minutes)
MORTENSON's other public contracts
More Port Of Bremerton contracts
Questions about this contract
Who was awarded the construction contract by Port Of Bremerton?
MORTENSON was awarded this construction contract by Port Of Bremerton, as recorded on July 14, 2026.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Port of Bremerton Minutes Regular Business Meeting July 14, 2026 (Minutes), dated July 14, 2026 from Port Of Bremerton. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does MORTENSON hold?
MORTENSON may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is Port Of Bremerton currently buying?
Explore Port Of Bremerton's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.