CONSTRUCTIONAMENDED

AD Morgan cooler-freezer project schedule extended

Marion County Public Schools approved a schedule change order with AD Morgan for the Cooler Freezer Project at Howard Academy, granting an additional 28 calendar days due to gas line relocation issues. The contract time now totals 148 calendar days with a revised substantial completion date of October 25, 2026.

Document date · July 14, 2026

Track Marion County School District contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Marion County School District.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract type
CONSTRUCTION
Contract term
Original contract time plus 28 additional calendar days; new total 148 calendar days with substantial completion date of 10/25/26
Renewal date
2026-10-25
Renewal
Change order extends contract time by 28 calendar days, revising total duration to 148 calendar days and substantial completion to 2026-10-25; no information is provided on further renewal or extension options.
Document type
Contract
Source document
Marion County Public Schools Contract Cooler Freezer Additions 2026-07-14

Related contracts

Other contracts from Ad Morgan.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Marion County School District?

Ad Morgan was awarded this construction contract by Marion County School District, as recorded on July 14, 2026.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Marion County Public Schools Contract Cooler Freezer Additions 2026-07-14 (Contract), dated July 14, 2026 from Marion County School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Ad Morgan hold?

Ad Morgan may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Ad Morgan's profile

What is Marion County School District currently buying?

Explore Marion County School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Marion County School District's profile