Harrison Avenue Demolition Change Order Approved for Ritschard
- Disclosed value
- Increase of $17,865; revised contract amount $552,788
- From bid award
- Document date
- Sep 22, 2026
The 30-second brief
The Board of Public Works approved a $17,865 change order for Ritschard Bros., Inc.'s demolition project at 747-749 Harrison Avenue. The change covers unforeseen asbestos abatement and concrete removal, increasing the contract to $552,788 and extending completion by 61 days to August 30, 2026.
Ritschard Brothers Inc holds this construction contract with City of South Bend. Its other public contracts on record include work for City of Three Rivers and Town of Indian Village.
Term as filed: Completion date extended by 61 days to August 30, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Increase of $17,865; revised contract amount $552,788
- Document date
- September 22, 2026
- Term
- Completion date extended by 61 days to August 30, 2026
- Vendor
- Ritschard Brothers Inc
- Agency
- City of South Bend
- Source document
- Change Order No 2 - Demolition of 747-749 Harrison Avenue Proj No 124-062 - Ritschard Bros (Bid Award)
Ritschard Brothers Inc's other public contracts
More City of South Bend contracts
Questions about this contract
Who was awarded the construction contract by City of South Bend?
Ritschard Brothers Inc was awarded this construction contract by City of South Bend, as recorded on September 22, 2026. The contract value is Increase of $17,865; revised contract amount $552,788.
How much is the Ritschard Brothers Inc contract with City of South Bend worth?
The Ritschard Brothers Inc contract with City of South Bend is valued at Increase of $17,865; revised contract amount $552,788, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a bid award record.
Where was this contract approved?
This contract appears in Change Order No 2 - Demolition of 747-749 Harrison Avenue Proj No 124-062 - Ritschard Bros (Bid Award), dated September 22, 2026 from City of South Bend. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Ritschard Brothers Inc hold?
Ritschard Brothers Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of South Bend currently buying?
Explore City of South Bend's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.