Malibu Adds Asphalt Repairs to Lee Construction Contract
City of MalibuCity · Malibu, CA- Disclosed value
- $19,554 change order; revised construction total $549,390
- From staffreport
- Document date
- Aug 24, 2026
- Term
- Issued during construction in 2026
The 30-second brief
The City of Malibu amended Lee Construction’s Westward Beach Road repair contract by $19,554 for additional asphalt repairs. The change order increased the total construction cost to $549,390 and remained within the project budget.
Lee Construction holds this construction contract with City of Malibu. Its other public contracts on record include work for City of Satanta and City of Garden.
Term as filed: Issued during construction in 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $19,554 change order; revised construction total $549,390
- Document date
- August 24, 2026
- Term
- Issued during construction in 2026
- Vendor
- Lee Construction
- Agency
- City of Malibu
- Source document
- City of Malibu StaffReport Acceptance of Westward Beach Road Embankment Repairs Project 2026-08-24 (StaffReport)
Lee Construction's other public contracts
More City of Malibu contracts
Questions about this contract
Who was awarded the construction contract by City of Malibu?
Lee Construction was awarded this construction contract by City of Malibu, as recorded on August 24, 2026. The contract value is $19,554 change order; revised construction total $549,390.
How much is the Lee Construction contract with City of Malibu worth?
The Lee Construction contract with City of Malibu is valued at $19,554 change order; revised construction total $549,390, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a staffreport record.
Where was this contract approved?
This contract appears in City of Malibu StaffReport Acceptance of Westward Beach Road Embankment Repairs Project 2026-08-24 (StaffReport), dated August 24, 2026 from City of Malibu. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Lee Construction hold?
Lee Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Malibu currently buying?
Explore City of Malibu's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.