Brighton Central School District 2023 Capital Improvement Project Phase 2 Monthly Progress Report March 2026

Concord Advances Electrical Work in Boiler Room

Brighton Central School DistrictCONCORDMarch 31, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Concord, serving as the Phase 2 electrical contractor, ran conduit, installed panels, and provided power to mechanical and plumbing units in the Brighton High School boiler room during March 2026. The work forms part of the district’s multi-prime Phase 2 capital improvements.

Contract Details

Vendor

CONCORD

Agency

Brighton Central School District, NY

Contract Type

CONSTRUCTION

Document Date

March 31, 2026

Contract Term

Phase 2 Electrical Contractor (EC) activities during March 2026