Airport Approves Triton Drainage Contract Change Order
- Disclosed value
- Net increase of $8,389.18; revised contract total of $2,465,498.36
- From minutes
- Document date
- Jul 22, 2026
The 30-second brief
The Authority approved a $8,389.18 increase to Triton Construction’s Airport Drainage Phase 1 contract, raising the revised total to $2,465,498.36. The change order adds under-drainpipe and field-condition work and extends the revised contract time to 195 calendar days.
Triton Construction Inc holds this construction contract with Yeager Airport Authority. Its other public contracts on record include work for Kentucky Division of Construction | Commonwealth of Kentucky and City of Marietta.
Term as filed: Revised total contract time of 195 calendar days.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Net increase of $8,389.18; revised contract total of $2,465,498.36
- Document date
- July 22, 2026
- Term
- Revised total contract time of 195 calendar days
- Vendor
- Triton Construction Inc
- Agency
- Yeager Airport Authority
- Source document
- Central West Virginia Regional Airport Authority Minutes Board Meeting 2026-07-22 (Minutes)
Triton Construction Inc's other public contracts
More Yeager Airport Authority contracts
Questions about this contract
Who was awarded the construction contract by Yeager Airport Authority?
Triton Construction Inc was awarded this construction contract by Yeager Airport Authority, as recorded on July 22, 2026. The contract value is Net increase of $8,389.18; revised contract total of $2,465,498.36.
How much is the Triton Construction Inc contract with Yeager Airport Authority worth?
The Triton Construction Inc contract with Yeager Airport Authority is valued at Net increase of $8,389.18; revised contract total of $2,465,498.36, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Central West Virginia Regional Airport Authority Minutes Board Meeting 2026-07-22 (Minutes), dated July 22, 2026 from Yeager Airport Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Triton Construction Inc hold?
Triton Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Yeager Airport Authority currently buying?
Explore Yeager Airport Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.