CONSTRUCTIONRECOMMENDED

Heller Spillway Change Order 2 Extends Completion Date

The Planning/Operations Committee reviewed Change Order #2 with Greenland Construction, Inc. for the Heller Spillway Project, recommending approval of a 145-day winter shutdown extension to May 20, 2026 with no additional cost. Work is planned to resume on March 15, 2026.

Document date · January 14, 2026

Track Williamsport Municipal Water Authority & Williamsport Sanitary Authority contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Williamsport Municipal Water Authority & Williamsport Sanitary Authority.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract type
CONSTRUCTION
Contract term
Substantial completion date extended from December 27, 2025 to May 20, 2026; work to resume March 15, 2026
Renewal date
2026-05-20
Renewal
Change Order #2 extends the substantial completion deadline by 145 days due to an approved winter shutdown, with no change to contract price.
Document type
Minutes
Source document
Williamsport Municipal Water Authority Minutes of Planning / Operations Committee 2026-01-14

Related contracts

Other contracts from Greenland Construction Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Williamsport Municipal Water Authority & Williamsport Sanitary Authority?

Greenland Construction Inc was awarded this construction contract by Williamsport Municipal Water Authority & Williamsport Sanitary Authority, as recorded on January 14, 2026.

What type of contract is this?

This is a Construction contract, documented as a minutes record.

Where was this contract approved?

This contract appears in Williamsport Municipal Water Authority Minutes of Planning / Operations Committee 2026-01-14 (Minutes), dated January 14, 2026 from Williamsport Municipal Water Authority & Williamsport Sanitary Authority. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Greenland Construction Inc hold?

Greenland Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Greenland Construction Inc's profile

What is Williamsport Municipal Water Authority & Williamsport Sanitary Authority currently buying?

Explore Williamsport Municipal Water Authority & Williamsport Sanitary Authority's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Williamsport Municipal Water Authority & Williamsport Sanitary Authority's profile