South Coast Water District awarded Big Ben, Inc. a $1,688,433 construction contract for the Mission Hospital Pipeline Improvements Project. The Board authorized up to $168,843 in change orders.

Document date · October 5, 2026

Track South Coast Water District contracts

Get alerts when new contracts are awarded or existing ones approach renewal at South Coast Water District.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$1,688,433; change orders up to $168,843 authorized
Contract type
CONSTRUCTION
Contract term
Construction was scheduled for 100 working days, with completion initially anticipated in March 2026 and field work later extended through August 2026
Renewal date
2026-10-31
Renewal
The construction schedule was extended by design changes and construction delays, with field work completed through August 2026 and project closeout anticipated in October 2026.
Document type
StaffReport
Source document
South Coast Water District Staff Report Mission Hospital Pipeline Improvements Project - Construction Management Services Contract Amendment For AKM Consulting Engineers 2026-10-05

Related contracts

Other contracts from Big Ben Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by South Coast Water District?

Big Ben Inc was awarded this construction contract by South Coast Water District, as recorded on October 5, 2026. The contract value is $1,688,433; change orders up to $168,843 authorized.

How much is the Big Ben Inc contract with South Coast Water District worth?

The Big Ben Inc contract with South Coast Water District is valued at $1,688,433; change orders up to $168,843 authorized, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record.

Where was this contract approved?

This contract appears in South Coast Water District Staff Report Mission Hospital Pipeline Improvements Project - Construction Management Services Contract Amendment For AKM Consulting Engineers 2026-10-05 (StaffReport), dated October 5, 2026 from South Coast Water District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Big Ben Inc hold?

Big Ben Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Big Ben Inc's profile

What is South Coast Water District currently buying?

Explore South Coast Water District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View South Coast Water District's profile