Briarcrest Phase 2 construction contract change order approved
- Disclosed value
- $754.11 (excluding WSST); new total $867,791.09
- From staffreport
- Document date
- Mar 3, 2026
The 30-second brief
The Shoreline Board is asked to approve Change Order #02 with CDK Construction Services for Phase 2 of the Briarcrest Elementary School Modernization Project, adding $754.11 (excluding WSST) for additional audio visual system tuning. The amendment increases the construction contract total to $867,791.09 while staying within the previously authorized project budget, funded through the Capital Projects Fund – 2006 Bond Authorization.
Cdk Construction Services holds this construction contract with Shoreline School District. Its other public contracts on record include work for Covington County Water Authority and City of Oak Harbor.
Hear about the next contract at Shoreline School District early.
Get pre-RFP alerts freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $754.11 (excluding WSST); new total $867,791.09
- Document date
- March 3, 2026
- Source document
- Shoreline Board of Directors StaffReport Briarcrest Elementary School Modernization Project Change Order 2026-03-03 (StaffReport)
Cdk Construction Services's other public contracts
More Shoreline School District contracts
Questions about this contract
Who was awarded the construction contract by Shoreline School District?
Cdk Construction Services was awarded this construction contract by Shoreline School District, as recorded on March 3, 2026. The contract value is $754.11 (excluding WSST); new total $867,791.09.
How much is the Cdk Construction Services contract with Shoreline School District worth?
The Cdk Construction Services contract with Shoreline School District is valued at $754.11 (excluding WSST); new total $867,791.09, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a staffreport record.
Where was this contract approved?
This contract appears in Shoreline Board of Directors StaffReport Briarcrest Elementary School Modernization Project Change Order 2026-03-03 (StaffReport), dated March 3, 2026 from Shoreline School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Cdk Construction Services hold?
Cdk Construction Services may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Shoreline School District currently buying?
Explore Shoreline School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.