Anderson Excavating Submits Clearwater Pay Estimate
Red Lake Watershed DistrictSpecial District · Thief River Falls, MN- Disclosed value
- $897,705.13 original contract; $792,404.48 work completed; $119,071.88 current payment amount
- From report
- Document date
- Oct 27, 2026
- Term
- August 17, 2026 – July 30, 2027
- Renews
- Free account
The 30-second brief
Quality Spray Foam LLC/dba Anderson Excavating submitted Pay Estimate No. 4 for Clearwater River Stabilization. The project has an original contract value of $897,705.13 and reported completed work of $792,404.48.
Quality Spray Foam LLC Dba Anderson Excavating holds this construction contract with Red Lake Watershed District.
The renewal date is on record. Get free alerts for pre-RFPs like this one, matched to what you sell.
Get pre-RFPs for work like this before the bid is out.
Get pre-RFP alerts freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $897,705.13 original contract; $792,404.48 work completed; $119,071.88 current payment amount
- Document date
- October 27, 2026
- Term
- August 17, 2026 – July 30, 2027
- Renews
- On record
- Source document
- Red Lake Watershed District Report Mud River Watershed Preliminary Investigation Findings Report 2026-10-27 (Report)
Quality Spray Foam LLC Dba Anderson Excavating's other public contracts
More Red Lake Watershed District contracts
Questions about this contract
Who was awarded the construction contract by Red Lake Watershed District?
Quality Spray Foam LLC Dba Anderson Excavating was awarded this construction contract by Red Lake Watershed District, as recorded on October 27, 2026. The contract value is $897,705.13 original contract; $792,404.48 work completed; $119,071.88 current payment amount.
How much is the Quality Spray Foam LLC Dba Anderson Excavating contract with Red Lake Watershed District worth?
The Quality Spray Foam LLC Dba Anderson Excavating contract with Red Lake Watershed District is valued at $897,705.13 original contract; $792,404.48 work completed; $119,071.88 current payment amount, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Red Lake Watershed District Report Mud River Watershed Preliminary Investigation Findings Report 2026-10-27 (Report), dated October 27, 2026 from Red Lake Watershed District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Quality Spray Foam LLC Dba Anderson Excavating hold?
Quality Spray Foam LLC Dba Anderson Excavating may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Red Lake Watershed District currently buying?
Explore Red Lake Watershed District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.