CONTRACTAPPROVED

Mascoutah CUD 19 Awards Construction Contract to Poettker Construction Company (November 2026)

Mascoutah CUD 19 logoMascoutah CUD 19
Disclosed value
$0.00 change order; original and revised contract sum $20,248,000.00
From contract
Approved
Nov 17, 2026

The 30-second brief

What it covers

Mascoutah CUSD 19 approved Change Order #002 with Poettker Construction Company for ASI-007 electrical changes at the Mascoutah High School addition and renovation. The change order has a net value of $0.00 because $23,840.00 is shifted from contingency, leaving the total contract at $20,248,000.00 with no schedule impact.

Who holds it

Poettker Construction Company holds this construction contract with Mascoutah CUD 19. Its other public contracts on record include work for State of Illinois and Parkway C-2 School District.

Hear about the next contract at Mascoutah CUD 19 early.

Get pre-RFP alerts free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$0.00 change order; original and revised contract sum $20,248,000.00
Document date
November 17, 2026
Source document
Mascoutah CUSD 19 Contract Prime Contract Change Order #002: ASI-007 Electric Changes 2026-11-17 (Contract)

Poettker Construction Company's other public contracts

More Mascoutah CUD 19 contracts

Questions about this contract

Who was awarded the construction contract by Mascoutah CUD 19?

Poettker Construction Company was awarded this construction contract by Mascoutah CUD 19, as recorded on November 17, 2026. The contract value is $0.00 change order; original and revised contract sum $20,248,000.00.

How much is the Poettker Construction Company contract with Mascoutah CUD 19 worth?

The Poettker Construction Company contract with Mascoutah CUD 19 is valued at $0.00 change order; original and revised contract sum $20,248,000.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Mascoutah CUSD 19 Contract Prime Contract Change Order #002: ASI-007 Electric Changes 2026-11-17 (Contract), dated November 17, 2026 from Mascoutah CUD 19. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Poettker Construction Company hold?

Poettker Construction Company may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Mascoutah CUD 19 currently buying?

Explore Mascoutah CUD 19's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →

The coverage behind every signal

agencies covered
275,000+agencies covered
buying signals a week
400,000+buying signals a week
decision makers
2.6M+decision makers
in government spend tracked
$14T+in government spend tracked

Trusted by 200+ enterprise teams

Motive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logo