CONTRACTAPPROVED

Lone Oak Farm Mud Awards Construction Contract to Ram Utilities LLP (October 2026)

Lone Oak Farm Mud
Disclosed value
Change Order No. 3: $1,850; Phase 1 Pay Estimates Nos. 3-12 and Phase 2 Pay Estimate No. 4: amounts stated individually in the packet; Pay Estimate No. 12: $13,809.96 final
From packet
Approved
Oct 19, 2026

The 30-second brief

What it covers

The District approved and advanced closeout payments for Ram Utilities’ Navarro Sewer Extension Phases 1 and 2 project. The engineer recommended the final $13,809.96 Phase 1 payment and acceptance of the completed project.

Who holds it

Ram Utilities LLP holds this construction contract with Lone Oak Farm Mud.

Hear about the next contract at Lone Oak Farm Mud early.

Get pre-RFP alerts free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Change Order No. 3: $1,850; Phase 1 Pay Estimates Nos. 3-12 and Phase 2 Pay Estimate No. 4: amounts stated individually in the packet; Pay Estimate No. 12: $13,809.96 final
Document date
October 19, 2026
Source document
Lone Oak Farm Municipal Utility District Packet October 20, 2026 (Packet)

Ram Utilities LLP's other public contracts

More Lone Oak Farm Mud contracts

Questions about this contract

Who was awarded the construction contract by Lone Oak Farm Mud?

Ram Utilities LLP was awarded this construction contract by Lone Oak Farm Mud, as recorded on October 19, 2026. The contract value is Change Order No. 3: $1,850; Phase 1 Pay Estimates Nos. 3-12 and Phase 2 Pay Estimate No. 4: amounts stated individually in the packet; Pay Estimate No. 12: $13,809.96 final.

How much is the Ram Utilities LLP contract with Lone Oak Farm Mud worth?

The Ram Utilities LLP contract with Lone Oak Farm Mud is valued at Change Order No. 3: $1,850; Phase 1 Pay Estimates Nos. 3-12 and Phase 2 Pay Estimate No. 4: amounts stated individually in the packet; Pay Estimate No. 12: $13,809.96 final, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a packet record.

Where was this contract approved?

This contract appears in Lone Oak Farm Municipal Utility District Packet October 20, 2026 (Packet), dated October 19, 2026 from Lone Oak Farm Mud. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Ram Utilities LLP hold?

Ram Utilities LLP may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Lone Oak Farm Mud currently buying?

Explore Lone Oak Farm Mud's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →

The coverage behind every signal

agencies covered
275,000+agencies covered
buying signals a week
400,000+buying signals a week
decision makers
2.6M+decision makers
in government spend tracked
$14T+in government spend tracked

Trusted by 200+ enterprise teams

Motive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logo