Little Silver Approves G Meyer Group Construction Change Order
- Disclosed value
- $0.00 net change; $1,654.00 PCO 8 cost charged against owner's discretionary allowance; new Contract Sum $714,715.00
- From contract
- Document date
- Sep 22, 2026
The 30-second brief
Little Silver Board of Education amended its construction contract with G Meyer Group through Change Order No. 004 for $1,654 in troubleshooting work related to the owner's building management system vendor. The cost is charged against the owner's discretionary allowance, leaving the total contract amount unchanged at $714,715, while completion time increases by one day to August 25, 2026.
G Meyer Group holds this construction contract with Little Silver Boro School District. Its other public contracts on record include work for Township of Middletown.
Term as filed: Contract Time increased by one (1) day; new date of Substantial Completion August 25, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $0.00 net change; $1,654.00 PCO 8 cost charged against owner's discretionary allowance; new Contract Sum $714,715.00
- Document date
- September 22, 2026
- Term
- Contract Time increased by one (1) day; new date of Substantial Completion August 25, 2026
- Vendor
- G Meyer Group
- Source document
- Little Silver Board of Education Contract Change Order 25.149 - LTS Point Road Ceiling Replacements & Interior Renovations 2026-09-22 (Contract)
G Meyer Group's other public contracts
More Little Silver Boro School District contracts
Questions about this contract
Who was awarded the construction contract by Little Silver Boro School District?
G Meyer Group was awarded this construction contract by Little Silver Boro School District, as recorded on September 22, 2026. The contract value is $0.00 net change; $1,654.00 PCO 8 cost charged against owner's discretionary allowance; new Contract Sum $714,715.00.
How much is the G Meyer Group contract with Little Silver Boro School District worth?
The G Meyer Group contract with Little Silver Boro School District is valued at $0.00 net change; $1,654.00 PCO 8 cost charged against owner's discretionary allowance; new Contract Sum $714,715.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in Little Silver Board of Education Contract Change Order 25.149 - LTS Point Road Ceiling Replacements & Interior Renovations 2026-09-22 (Contract), dated September 22, 2026 from Little Silver Boro School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does G Meyer Group hold?
G Meyer Group may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Little Silver Boro School District currently buying?
Explore Little Silver Boro School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.