CONSTRUCTIONAMENDED

Little Silver Approves G Meyer Group Construction Change Order

Little Silver Board of Education approved Change Order 003 with G Meyer Group for $2,167 in lighting-related soffit modifications and custom filler trim. The cost is charged against the owner's discretionary allowance, so the contract total remains $714,715, while the substantial completion date increases by two days to August 24, 2026.

Document date · September 15, 2026

Track Little Silver Boro School District contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Little Silver Boro School District.

Get started free

Create a free account · no credit card

Trusted by 200+ enterprise customers and 1,000+ teams on the free plan

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$2,167.00 change order cost; $0.00 net change to Contract Sum; new Contract Sum remains $714,715.00
Contract type
CONSTRUCTION
Contract term
Contract Time increased by two (2) days; new date of Substantial Completion: August 24, 2026
Renewal date
2026-08-24
Renewal
Contract time extended by two days; new substantial completion date is August 24, 2026. No increase to the overall Contract Sum.
Document type
Contract
Source document
Little Silver Board of Education Contract Change Order 003 2026-09-15

Related contracts

Other contracts from G Meyer Group.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Little Silver Boro School District?

G Meyer Group was awarded this construction contract by Little Silver Boro School District, as recorded on September 15, 2026. The contract value is $2,167.00 change order cost; $0.00 net change to Contract Sum; new Contract Sum remains $714,715.00.

How much is the G Meyer Group contract with Little Silver Boro School District worth?

The G Meyer Group contract with Little Silver Boro School District is valued at $2,167.00 change order cost; $0.00 net change to Contract Sum; new Contract Sum remains $714,715.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Little Silver Board of Education Contract Change Order 003 2026-09-15 (Contract), dated September 15, 2026 from Little Silver Boro School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does G Meyer Group hold?

G Meyer Group may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View G Meyer Group's profile

What is Little Silver Boro School District currently buying?

Explore Little Silver Boro School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Little Silver Boro School District's profile