Vinton Construction Change Order Extends Street Project Deadlines

Jackson village
Document date
Nov 22, 2026

The 30-second brief

What it covers

The Board of Public Works recommended that the Village Board approve Change Order #1 with Vinton Construction for the 2026 street improvement projects. The change order extends milestone completion deadlines because of utility, excavation, and street-lighting material delays, with no change in contract price.

Who holds it

Vinton Construction holds this construction contract with Jackson village.

What happens next

Term as filed: Milestone 1 substantial completion extended 35 days; Milestone 1 final completion extended 50 days; Milestone 2 substantial completion extended 238 days; Milestone 2 final completion extended 254 days.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Document date
November 22, 2026
Term
Milestone 1 substantial completion extended 35 days; Milestone 1 final completion extended 50 days; Milestone 2 substantial completion extended 238 days; Milestone 2 final completion extended 254 days
Source document
Village of Jackson AgendaPacket Board of Public Works Meeting November 24, 2026 (AgendaPacket)

Vinton Construction's other public contracts

More Jackson village contracts

Questions about this contract

Who was awarded the construction contract by Jackson village?

Vinton Construction was awarded this construction contract by Jackson village, as recorded on November 22, 2026.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Village of Jackson AgendaPacket Board of Public Works Meeting November 24, 2026 (AgendaPacket), dated November 22, 2026 from Jackson village. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Vinton Construction hold?

Vinton Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

Show 1 more question

What is Jackson village currently buying?

Explore Jackson village's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →

The coverage behind every signal

agencies covered
275,000+agencies covered
buying signals a week
400,000+buying signals a week
decision makers
2.6M+decision makers
in government spend tracked
$14T+in government spend tracked

Trusted by 200+ enterprise teams

Motive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logo