CONSTRUCTIONAMENDED

Unit price change orders reconciled with Lugaila Mechanical

Elizabeth Forward School District documents a comprehensive unit price reconciliation with Lugaila Mechanical for mechanical and related work under AIA Change Orders HC-2, HC-3, HC-4, and HC-8, totaling $226,860.00 in allowances fully deducted to a zero remaining balance. The amendment covers additional quantities of ductwork, insulated piping, mechanical equipment, ceiling grid/tile, and VCT removal/replacement within the existing construction contract.

Document date · August 5, 2026

Track Elizabeth Forward SD contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Elizabeth Forward SD.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$226,860.00 (unit price schedule; amounts reallocated via Change Orders HC-2, HC-3, HC-4, HC-8 resulting in $0.00 remaining balance)
Contract type
CONSTRUCTION
Renewal
The existing construction contract with Lugaila Mechanical is amended via AIA Change Orders HC-2, HC-3, HC-4, and HC-8 to utilize and deduct specified unit price allowances for additional mechanical and architectural work, resulting in no remaining unit price balance. No explicit renewal or extension terms are stated in this document.
Document type
Contract
Source document
Elizabeth Forward School District Change Order HC-8 2026-08-05

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Elizabeth Forward SD?

Lugaila Mechanical was awarded this construction contract by Elizabeth Forward SD, as recorded on August 5, 2026. The contract value is $226,860.00 (unit price schedule; amounts reallocated via Change Orders HC-2, HC-3, HC-4, HC-8 resulting in $0.00 remaining balance).

How much is the Lugaila Mechanical contract with Elizabeth Forward SD worth?

The Lugaila Mechanical contract with Elizabeth Forward SD is valued at $226,860.00 (unit price schedule; amounts reallocated via Change Orders HC-2, HC-3, HC-4, HC-8 resulting in $0.00 remaining balance), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Elizabeth Forward School District Change Order HC-8 2026-08-05 (Contract), dated August 5, 2026 from Elizabeth Forward SD. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Lugaila Mechanical hold?

Lugaila Mechanical may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Lugaila Mechanical's profile

What is Elizabeth Forward SD currently buying?

Explore Elizabeth Forward SD's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Elizabeth Forward SD's profile