Medium Voltage Relocation Change Order Approved
- Disclosed value
- $80,587.50 (change order amount $80,587.50; new contract sum $14,828,887.50)
- From contract
- Document date
- Jun 17, 2026
- Term
- No change in contract duration (0 days)
The 30-second brief
Richland County School District issued Change Order 03 with GeoSurfaces, Inc to relocate medium voltage electrical equipment at Richland County High School, increasing the contract by $80,587.50 with no change to the project duration. The new overall contract sum is $14,828,887.50.
Geosurfaces Inc holds this construction contract with Richland County CUSD 1. Its other public contracts on record include work for Seminole County and State of Louisiana.
Term as filed: No change in contract duration (0 days).
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $80,587.50 (change order amount $80,587.50; new contract sum $14,828,887.50)
- Document date
- June 17, 2026
- Term
- No change in contract duration (0 days)
- Vendor
- Geosurfaces Inc
- Agency
- Richland County CUSD 1
- Source document
- Richland Co School District Contract Change Order 03 2026-06-17 (Contract)
Geosurfaces Inc's other public contracts
More Richland County CUSD 1 contracts
Questions about this contract
Who was awarded the construction contract by Richland County CUSD 1?
Geosurfaces Inc was awarded this construction contract by Richland County CUSD 1, as recorded on June 17, 2026. The contract value is $80,587.50 (change order amount $80,587.50; new contract sum $14,828,887.50).
How much is the Geosurfaces Inc contract with Richland County CUSD 1 worth?
The Geosurfaces Inc contract with Richland County CUSD 1 is valued at $80,587.50 (change order amount $80,587.50; new contract sum $14,828,887.50), covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in Richland Co School District Contract Change Order 03 2026-06-17 (Contract), dated June 17, 2026 from Richland County CUSD 1. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Geosurfaces Inc hold?
Geosurfaces Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Richland County CUSD 1 currently buying?
Explore Richland County CUSD 1's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.