Dallas Board Accepts Gaston Renovation Change Order
- Disclosed value
- Change Order #1: -$83,237.49 credit; revised contract amount $4,824,888.51; final payment $14,476.93
- From staffreport
- Document date
- Nov 15, 2026
The 30-second brief
Dallas Independent School District accepted completion of TM Source Building Group, Inc.'s W.H. Gaston Middle School renovation, approved a $83,237.49 contract credit, and authorized a $14,476.93 final payment from Bond Funds. The change order reduced the contract to $4,824,888.51 and extended substantial completion by 761 days to February 2, 2026.
Tm Source Building Group Inc holds this construction contract with Dallas Independent School District.
Term as filed: April 17, 2023 – February 2, 2026; substantial completion extended by 761 days.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Change Order #1: -$83,237.49 credit; revised contract amount $4,824,888.51; final payment $14,476.93
- Document date
- November 15, 2026
- Term
- April 17, 2023 – February 2, 2026; substantial completion extended by 761 days
- Source document
- Dallas Independent School District StaffReport Contract Completion and Change Order for W.H. Gaston Middle School 2026-11-19 (StaffReport)
Tm Source Building Group Inc's other public contracts
More Dallas Independent School District contracts
Questions about this contract
Who was awarded the construction contract by Dallas Independent School District?
Tm Source Building Group Inc was awarded this construction contract by Dallas Independent School District, as recorded on November 15, 2026. The contract value is Change Order #1: -$83,237.49 credit; revised contract amount $4,824,888.51; final payment $14,476.93.
How much is the Tm Source Building Group Inc contract with Dallas Independent School District worth?
The Tm Source Building Group Inc contract with Dallas Independent School District is valued at Change Order #1: -$83,237.49 credit; revised contract amount $4,824,888.51; final payment $14,476.93, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a staffreport record.
Where was this contract approved?
This contract appears in Dallas Independent School District StaffReport Contract Completion and Change Order for W.H. Gaston Middle School 2026-11-19 (StaffReport), dated November 15, 2026 from Dallas Independent School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Tm Source Building Group Inc hold?
Tm Source Building Group Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Dallas Independent School District currently buying?
Explore Dallas Independent School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.