Marla Park Construction Change Order Proposed for Southern Remodeling
- Disclosed value
- Change order increase of $43,032.00; $6,768.00 credit and $49,800.00 irrigation add; revised contract sum $849,272.00
- From contract
- Document date
- Sep 4, 2026
The 30-second brief
The City of Palmview proposed Change Order No. 002 with Southern Remodeling & Construction LLC for the Marla Park project. The change would increase the contract by $43,032, bringing the total to $849,272, and extend the schedule by 44 working days to October 30, 2026 for substantial completion.
Southern Remodeling & Construction LLC holds this construction contract with City of Palmview.
Term as filed: 44 additional working days; proposed substantial completion October 30, 2026; proposed final completion November 30, 2026.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Change order increase of $43,032.00; $6,768.00 credit and $49,800.00 irrigation add; revised contract sum $849,272.00
- Document date
- September 4, 2026
- Term
- 44 additional working days; proposed substantial completion October 30, 2026; proposed final completion November 30, 2026
- Vendor
- Southern Remodeling & Construction LLC
- Agency
- City of Palmview
- Source document
- City of Palmview Contract Change Order No. 002 Marla Park 2026-09-04 (Contract)
Southern Remodeling & Construction LLC's other public contracts
More City of Palmview contracts
Questions about this contract
Who was awarded the construction contract by City of Palmview?
Southern Remodeling & Construction LLC was awarded this construction contract by City of Palmview, as recorded on September 4, 2026. The contract value is Change order increase of $43,032.00; $6,768.00 credit and $49,800.00 irrigation add; revised contract sum $849,272.00.
How much is the Southern Remodeling & Construction LLC contract with City of Palmview worth?
The Southern Remodeling & Construction LLC contract with City of Palmview is valued at Change order increase of $43,032.00; $6,768.00 credit and $49,800.00 irrigation add; revised contract sum $849,272.00, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a contract record.
Where was this contract approved?
This contract appears in City of Palmview Contract Change Order No. 002 Marla Park 2026-09-04 (Contract), dated September 4, 2026 from City of Palmview. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 1 more question
What is City of Palmview currently buying?
Explore City of Palmview's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.