CONTRACTPENDING

Marla Park Construction Change Order Proposed for Southern Remodeling

City of Palmview logoCity of Palmview
Disclosed value
Change order increase of $43,032.00; $6,768.00 credit and $49,800.00 irrigation add; revised contract sum $849,272.00
From contract
Document date
Sep 4, 2026

The 30-second brief

What it covers

The City of Palmview proposed Change Order No. 002 with Southern Remodeling & Construction LLC for the Marla Park project. The change would increase the contract by $43,032, bringing the total to $849,272, and extend the schedule by 44 working days to October 30, 2026 for substantial completion.

Who holds it

Southern Remodeling & Construction LLC holds this construction contract with City of Palmview.

What happens next

Term as filed: 44 additional working days; proposed substantial completion October 30, 2026; proposed final completion November 30, 2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
Change order increase of $43,032.00; $6,768.00 credit and $49,800.00 irrigation add; revised contract sum $849,272.00
Document date
September 4, 2026
Term
44 additional working days; proposed substantial completion October 30, 2026; proposed final completion November 30, 2026
Vendor
Southern Remodeling & Construction LLC
Source document
City of Palmview Contract Change Order No. 002 Marla Park 2026-09-04 (Contract)

Southern Remodeling & Construction LLC's other public contracts

More City of Palmview contracts

Questions about this contract

Who was awarded the construction contract by City of Palmview?

Southern Remodeling & Construction LLC was awarded this construction contract by City of Palmview, as recorded on September 4, 2026. The contract value is Change order increase of $43,032.00; $6,768.00 credit and $49,800.00 irrigation add; revised contract sum $849,272.00.

How much is the Southern Remodeling & Construction LLC contract with City of Palmview worth?

The Southern Remodeling & Construction LLC contract with City of Palmview is valued at Change order increase of $43,032.00; $6,768.00 credit and $49,800.00 irrigation add; revised contract sum $849,272.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in City of Palmview Contract Change Order No. 002 Marla Park 2026-09-04 (Contract), dated September 4, 2026 from City of Palmview. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 1 more question

What is City of Palmview currently buying?

Explore City of Palmview's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →

The coverage behind every signal

agencies covered
275,000+agencies covered
buying signals a week
400,000+buying signals a week
decision makers
2.6M+decision makers
in government spend tracked
$14T+in government spend tracked

Trusted by 200+ enterprise teams

Motive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logo