Mill Valley Accepts Completed Storm Drain Work

City of Mill Valley logoCity of Mill Valley
Disclosed value
$75,403 bid; final construction costs $83,983.05 including $8,580.05 in change orders
From staffreport
Document date
Sep 8, 2026

The 30-second brief

What it covers

The City of Mill Valley accepted completion of the Hillside Avenue Storm Drain Improvements Project performed by Precision Excavating & Grading, Inc. The original bid was $75,403, and final construction costs totaled $83,983.05 after change orders.

Who holds it

Precision Excavating & Grading Inc holds this construction contract with City of Mill Valley. Its other public contracts on record include work for Town of Windsor and Auburn Recreation And Park District.

What happens next

Term as filed: Authorized September 15, 2025; work began May 26, 2026; substantially complete August 4, 2026.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$75,403 bid; final construction costs $83,983.05 including $8,580.05 in change orders
Document date
September 8, 2026
Term
Authorized September 15, 2025; work began May 26, 2026; substantially complete August 4, 2026
Vendor
Precision Excavating & Grading Inc
Source document
City of Mill Valley StaffReport Notice of Completion Hillside Avenue Storm Drain Improvements Project 2026-09-08 (StaffReport)

Precision Excavating & Grading Inc's other public contracts

More City of Mill Valley contracts

Questions about this contract

Who was awarded the construction contract by City of Mill Valley?

Precision Excavating & Grading Inc was awarded this construction contract by City of Mill Valley, as recorded on September 8, 2026. The contract value is $75,403 bid; final construction costs $83,983.05 including $8,580.05 in change orders.

How much is the Precision Excavating & Grading Inc contract with City of Mill Valley worth?

The Precision Excavating & Grading Inc contract with City of Mill Valley is valued at $75,403 bid; final construction costs $83,983.05 including $8,580.05 in change orders, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record.

Where was this contract approved?

This contract appears in City of Mill Valley StaffReport Notice of Completion Hillside Avenue Storm Drain Improvements Project 2026-09-08 (StaffReport), dated September 8, 2026 from City of Mill Valley. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 1 more question

What is City of Mill Valley currently buying?

Explore City of Mill Valley's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →

The coverage behind every signal

agencies covered
275,000+agencies covered
buying signals a week
400,000+buying signals a week
decision makers
2.6M+decision makers
in government spend tracked
$14T+in government spend tracked

Trusted by 200+ enterprise teams

Motive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logo