Pino Lane Wastewater Contract Recommended for Facilities Rehabilitation
- Disclosed value
- $1,453,484 plus a $145,349 contingency; total contract amount not to exceed $1,598,833
- From staffreport
- Document date
- Nov 14, 2026
- Term
- 180 calendar days for completion
The 30-second brief
The City of Austin recommended awarding Facilities Rehabilitation, Inc. a construction contract for the Pino Lane Wastewater Improvements Project. The contract is valued at $1,453,484, with a $145,349 contingency for a total amount not to exceed $1,598,833, and allows 180 calendar days for completion.
Facilities Rehabilitation Inc holds this construction contract with City of Austin city.
Term as filed: 180 calendar days for completion.
See who decides the next one before it's bid.
Get pre-RFPs freeFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $1,453,484 plus a $145,349 contingency; total contract amount not to exceed $1,598,833
- Document date
- November 14, 2026
- Term
- 180 calendar days for completion
- Agency
- City of Austin city
- Source document
- City of Austin StaffReport Pino Lane Wastewater Improvements Project Contract Award 2026-11-19 (StaffReport)
Facilities Rehabilitation Inc's other public contracts
More City of Austin city contracts
Questions about this contract
Who was awarded the construction contract by City of Austin city?
Facilities Rehabilitation Inc was awarded this construction contract by City of Austin city, as recorded on November 14, 2026. The contract value is $1,453,484 plus a $145,349 contingency; total contract amount not to exceed $1,598,833.
How much is the Facilities Rehabilitation Inc contract with City of Austin city worth?
The Facilities Rehabilitation Inc contract with City of Austin city is valued at $1,453,484 plus a $145,349 contingency; total contract amount not to exceed $1,598,833, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a staffreport record, structured as a not-to-exceed (ceiling) agreement.
Where was this contract approved?
This contract appears in City of Austin StaffReport Pino Lane Wastewater Improvements Project Contract Award 2026-11-19 (StaffReport), dated November 14, 2026 from City of Austin city. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Facilities Rehabilitation Inc hold?
Facilities Rehabilitation Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Austin city currently buying?
Explore City of Austin city's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.