Verona clarifier upgrade contract change order approved
Trusted by teams at
Description
The Township of Verona Council approved Change Order No. 1 to Contract No. 2021-06 with Rapid Pump and Meter, increasing the contract by $42,528.96 to a total of $1,281,408.96. The amendment funds allowance reconciliations, SCADA improvements, and adds 182 calendar days, extending the project completion date to May 1, 2026.
Contract Details
Contract Amount
+$42,528.96 (final contract amount $1,281,408.96; original $1,238,880)
Vendor
RAPID PUMP & METER
Agency
Township of Verona, NJ
Contract Type
CONSTRUCTION
Document Date
April 6, 2026
Contract Term
Contract completion date extended from October 31, 2025 to May 1, 2026 (additional 182 calendar days)
Renewal Date
2026-05-01
Renewal Info
Change Order No. 1 increases the contract value by 3.43% and extends the completion date by 182 days from October 31, 2025 to May 1, 2026.
More from RAPID PUMP & METER
More from Township of Verona
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.