Rapid Pump Contract Increased for Clarifier Upgrades
Trusted by teams at
Description
Verona Council approved a $42,528.96 change order with Rapid Pump and Meter for additional work on the Primary Clarifier Pump Station upgrades, bringing the total contract to $1,281,408.96. The amendment covers temporary pumping, unforeseen conditions, valve cleaning, and SCADA improvements.
Contract Details
Contract Amount
+ $42,528.96 (change order); new total $1,281,408.96
Vendor
RAPID PUMP & METER
Agency
Township of Verona, NJ
Contract Type
CONSTRUCTION
Document Date
April 6, 2026
Renewal Info
Change Order #1 increases the original 2024-awarded contract by 3.43% to a new total of $1,281,408.96; no extension of time is specified in the minutes.