CONTRACTONGOING

Hydro Resources completes MAR wells construction

Salt Lake-Sandy Metropolitan Water District logoSalt Lake-Sandy Metropolitan Water District
Disclosed value
$3,674,441.00 (with change orders totaling -$321,449.97; final paid $3,352,991.03)
From report
Document date
Apr 13, 2026
Term
Final completion June 30, 2024

The 30-second brief

What it covers

Hydro Resources completed well construction for Metro Water’s Managed Aquifer Recharge project under a $3.67 million contract, later reduced by $321,449.97 through change orders. The final construction value was $3,352,991.03 with work substantially completed by June 30, 2024.

Who holds it

Hydro Resources holds this construction contract with Salt Lake-Sandy Metropolitan Water District. Its other public contracts on record include work for City of Celina city and PANHANDLE GCD.

What happens next

Term as filed: Final completion June 30, 2024.

See who decides the next one before it's bid.

Get pre-RFPs free

Free account · 30-second setup · No credit card

Contract details

Contract type
Construction
Amount
$3,674,441.00 (with change orders totaling -$321,449.97; final paid $3,352,991.03)
Document date
April 13, 2026
Term
Final completion June 30, 2024
Source document
Metro Water Engineering Committee Report April 2026 (Report)

Hydro Resources's other public contracts

More Salt Lake-Sandy Metropolitan Water District contracts

Questions about this contract

Who was awarded the construction contract by Salt Lake-Sandy Metropolitan Water District?

Hydro Resources was awarded this construction contract by Salt Lake-Sandy Metropolitan Water District, as recorded on April 13, 2026. The contract value is $3,674,441.00 (with change orders totaling -$321,449.97; final paid $3,352,991.03).

How much is the Hydro Resources contract with Salt Lake-Sandy Metropolitan Water District worth?

The Hydro Resources contract with Salt Lake-Sandy Metropolitan Water District is valued at $3,674,441.00 (with change orders totaling -$321,449.97; final paid $3,352,991.03), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in Metro Water Engineering Committee Report April 2026 (Report), dated April 13, 2026 from Salt Lake-Sandy Metropolitan Water District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

Show 2 more questions

What other contracts does Hydro Resources hold?

Hydro Resources may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

What is Salt Lake-Sandy Metropolitan Water District currently buying?

Explore Salt Lake-Sandy Metropolitan Water District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

Work in government? Get Civic IQ free →

The coverage behind every signal

agencies covered
275,000+agencies covered
buying signals a week
400,000+buying signals a week
decision makers
2.6M+decision makers
in government spend tracked
$14T+in government spend tracked

Trusted by 200+ enterprise teams

Motive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logoMotive logoVeritone logoTerraCycle logoCyvl logoWithersRavenel logoDerivita logoSafeTouch logoIANS Research logoSewerAI logoProdigy Education logoEPR Fireworks logoFlow Labs logoCloudpermit logo