CONSTRUCTIONONGOING

Walker Construction Advancing Jersey Heights Stormwater Project

Walker Construction is carrying out the Jersey Heights Stormwater project for Morristown, installing stormwater conveyance piping, structures, grading, and sidewalk replacement. The project is on track for completion by August 21, with minimal change orders totaling about $7,000 related to utility conflicts.

Document date · August 17, 2026

Track Town of Morristown contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Town of Morristown.

Get started free

Create a free account · no credit card

Trusted by 200+ enterprise customers and 1,000+ teams on the free plan

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
approximately $280,000 (project total implied from 2.5% change orders totaling $7,000)
Contract type
CONSTRUCTION
Contract term
Construction expected to complete by 2026-08-21
Renewal date
2026-08-21
Renewal
Two change orders were approved for utility-related adjustments; no extension of overall project schedule beyond the 2026-08-21 completion target is indicated.
Document type
AgendaPacket
Source document
Town of Morristown Agenda Packet 2026-08-17

Related contracts

Other contracts from Walker Construction.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Town of Morristown?

Walker Construction was awarded this construction contract by Town of Morristown, as recorded on August 17, 2026. The contract value is approximately $280,000 (project total implied from 2.5% change orders totaling $7,000).

How much is the Walker Construction contract with Town of Morristown worth?

The Walker Construction contract with Town of Morristown is valued at approximately $280,000 (project total implied from 2.5% change orders totaling $7,000), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Town of Morristown Agenda Packet 2026-08-17 (AgendaPacket), dated August 17, 2026 from Town of Morristown. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Walker Construction hold?

Walker Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Walker Construction's profile

What is Town of Morristown currently buying?

Explore Town of Morristown's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Town of Morristown's profile