CONSTRUCTIONAMENDED

Northgate Wastewater Contract Amended With Change Orders

The Town’s Northgate wastewater project documentation reflects $798,777.09 in change orders for Kubricky-Jointa Lime, LLC. The amendments raise the Contract 1A project total from $23.148 million to $23.947 million.

Document date · September 16, 2026

Track Town of Chenango contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Town of Chenango.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$798,777.09 in approved change orders; revised project total $23,946,777.09
Contract type
CONSTRUCTION
Document type
Report
Source document
Town of Chenango Report Northgate Wastewater Treatment Plant Improvements Progress Package September 16, 2026

Related contracts

Other contracts from Kubricky-jointa Lime Llc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Town of Chenango?

Kubricky-jointa Lime Llc was awarded this construction contract by Town of Chenango, as recorded on September 16, 2026. The contract value is $798,777.09 in approved change orders; revised project total $23,946,777.09.

How much is the Kubricky-jointa Lime Llc contract with Town of Chenango worth?

The Kubricky-jointa Lime Llc contract with Town of Chenango is valued at $798,777.09 in approved change orders; revised project total $23,946,777.09, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in Town of Chenango Report Northgate Wastewater Treatment Plant Improvements Progress Package September 16, 2026 (Report), dated September 16, 2026 from Town of Chenango. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Kubricky-jointa Lime Llc hold?

Kubricky-jointa Lime Llc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Kubricky-jointa Lime Llc's profile

What is Town of Chenango currently buying?

Explore Town of Chenango's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Town of Chenango's profile